BRABANT FIGHTS AGAINST WATER
Veerse Gat Dam

The veerse gat dam
The
closure of this estuary by the barrier was more complex as originally
anticipated.
The main problem focuses on the given fact that during the change of tides
approximately 70-million m3 water flows through the Veerse Gat.
It is extremely difficult to build a barrier, which is able to sustain this two
daily flow of water.
Basis
the old techniques it would certainly fail due to the strong currents. So
they had to develop new techniques. However the major part of the dam was build
basis the old techniques.
At the Beverland site the major part of the barrage was constructed on the
shallows of sand bank called "Van Onrust" The barrage was protected
bye asphalt to minimise the effects of tides and weather caused sea state.
On
the location an asphalt
plant was set up for this project to have direct delivery of the asphalt
mixture available when required.
In this way logistics improved and eliminated the time consuming
transport delays.
But the main problem still exists. The final gap of 320 meters which need to be
closed.
The
huge amounts of water which are going in and out with the tides makes life
miserable for the construction of the last part of the barrier.
In 1959 all preparations are ready to close the last open part of the barrier.
The goal was to start with dumping stones and shingles on top of
zinkers to the treshols basis of the caissons. After finalizing this final 24
caissons were scuttled on the threshold.

Here you see the caissons and in the background you can
see the barrier.
The caissons were built in
a special construction dock close to the site of the barrage.
The differention compared
to normal caissons was that these caissons were provided with openings. Your
reaction will be that it is strange to provide openings in caissons. This is
true but as the caissons had to stop the water but also had to allow the tides
running in and out during the construction this facilitates the final
construction of the barrier. The
caissons were provided with gate valves to allow the water run through.
The last caisson was
scuttled on April 24.
The gate valves were closed
on April 27 and as from that moment on the sea and tidal range was of no more
influence to the backland.
In this way .... the Veersemeer was created