BRABANT FIGHTS AGAINST WATER
Oesterdam

The Oesterdam
The
Oesterdam is a secondary barrier between Tholen and Zuid-Beveland for the
closure of the eastern part of the
Oosterschelde. This barrier is with its lengths of
11 kilometres the longest dam of all Delta works!!! The dam forms with
the Philipsdam and the Markiezaatkade part
of the Compartimenteringswerken.
The
Oesterdam arranges for the separation of sea
and fresh water in the
Oosterschelde area.. This is very important for the fresh water balance in the
provinces of Zeeland and Brabant. But there are more reasons to build this dam.
It was a part of an agreement with Belgium that Holland allows for a tidalfree
Schelde- Rijnconnection. This dam was also for this purpose.
The
Oosterdam developed by the construction of the work locks of the Bergse Diepmaas
They
started with the construction of the work dock for the building of the Bergse
Diepsluis (locks) near the southern coast of the isle of Tholen. The tender
procedure started and on 1 July the work dock is ready.
Thereafter
the construction of the south dam starts. This is a 3,25 kilometres long dam
part and starts at the western
side of the Kreekraksluizen. The tender were completed at 10 June 1980
and the south dam is ready on the 30th of June 1982.
In
the middle of the Oesterdam also a dam was constructed
over the Speelmansplaten existing of a dam called the "Speelmansplaten
1" ( lenght 4,15 km) . This was a dam on the south side of the work dock.
There was a also a second dam
called the "Speelmansplaten 2 (length 1,25 km). The works started in June
1984 and in July 1985 the Speelmansplaten
1 was ready and the Speelmansplaten 2
finally completed in May 1986.
Between
the south dam and "Speelmansplaten 2" a one kilometre long
opening exists namely between the work dock and the coast of Tholen. This
opening was closed on 29 October 1982.
But they weren't ready yet because there was still one opening called the Tholense Gat open. This opening was between the work dock of Bergse Diepsluis and the coast Tholen. This hole is closed at 23 October 1985 .