BRABANT FIGHTS AGAINST WATER Sorry, your browser doesn't support Java(tm).

 

                Volkerakdam and Hellegatsplein

                                                

 

During the same period working the Grevelingsdam. Engineers of Rijkswaterstaat are preparing a few kilometres away a new project. With all efforts they are working on the closure of the Volkerak and the construction of improved roads and bridges. Rijkswaterstaat is performing this study to get the right balance in water.  The advantages are a disposal of the ice during the winter. There is also an improvement of the traffic situation in the Zeeland waters. These are the most important arguments to build this barrier.

The activities on the Volkerakdam and Hellegatsplein are completed in 1969. Now in the year 2000 the road connection between the border of  Hollands Diep and Haringvliet are very important for the traffic between Noord-Brabant and randstad Holland. The realization of the causeway covering  the Hellegatsplaten to Goeree-Overflakkee, over a distance of 4,5 kilometer, performed  according plan.

The work proceeded well due to the fact that tidal currents are now not existing anymore. in June 1958 specialized dredging contractors start with filling bases for the bridges. There is only a small opening left [ The Ventjagersgat ] but the opening is also closed in February 1959.   

At the beginning of 1959 the bridge over the Haringvliet was completed. After working very hard for years battling the elements there is finally a fast connection  between the mainland of the province of Zuid-Holland and the isle of  Goeree-Overflakkee.

In order to make the bridge cost efficient and for the general maintenance there was a toll charged for the first ten years. After the first 10 year the government will take over responsibility of the bridge and maintain it properly.

The Volkerak is very busy navigable water in Holland with allows for a very special approach once considering activities to hamper the traffic. Because it was part of the Schelde-Rijn channel Belgium is also involved in the planning for this operation. During the construction shipping traffic can not be restricted and therefore locks were build for the ships with large dimensions

A total of  3 locks were build  with a length of 320 meters and a width of 24 meters. The construction of the locks started  in July 1960. The cost was estimated to be 2,5 million Dutch Guilders. In 1965 the bridge and the locks are ready.

The volkerak locks.

Hereafter the barrier in the Volkerak was build. This barrier was closed with the same principle used at the  Veerse gat.

In 1969 it is the moment.........the Volkerak is ready!!!

 