BRABANT FIGHTS AGAINST WATER Sorry, your browser doesn't support Java(tm).

 

               Oosterschelde

 

                                                 

                                               Oosterschelde barrier (Eastern Scheldt barrier)

The largest, most expensive and difficult part of the Delta works was the construction of the  flood barrier Oosterschelde. This partly open barrier in the  Oosterschelde is considered to be "the eight's world wonder". The weir was constructed  between 1976 and 1986.

First of all the plans were different. It was the intention to close the Oosterschelde with a "conventional " barrier

The works started in April 1967. The workdock Schelphoek (Schouwen-Duivelland) en Sophia (North Beveland) and the work island Roggenplaat (1969), Neeltje Jans ( 1970) and Noordland (1971)were completed. After the construction of the connection barriers between the work dock and work islands at the end of 1973 a total 5 out of the 9 km wide  Oosterschelde was closed. What remained were three openings,  Hammen, Schaar van Roggenplaat en Roompot.  The intention was to closed them by using concrete blocs dumped by  cable car. The required twelve support towers for this cable car were positioned during 1972.

But why did they change the plans???. They changed under the influence and pressure of a large part of the population who protested against the complete closure of the Oosterschelde. The results of the protest activity under the name of  " Oosterschelde Open"  was that all final activities were postponed in July 1974, awaiting the final decision by the government.

A turbulent period started the Oosterschelde problem as priority on the  political agenda. The final decision toke a long time. A special commission was appointed to advise the government regarding the open or closed Oosterschelde.

Finally the government decided  not to build the conventional dam but a storm barrier with movable gates. As a direct consequence during the winterperiod  1976-1977 the support towers for the cable car were taken down.

The new plan to construct storm barrier existed of huge concrete pillars resting on the seabed of the Oosterschelde . Between the pillars the steel movable gates were positioned which can close the Oosterschelde completely during a storm surge. On the weir a road is constructed of various different concrete elements.

The construction started in 1978 from the work island  Neeltje Jans which could be reached  from Schouwen-duivelland by a temporary road bridge with a length of 2780 m . Next was the  construction of the building dock where the concrete pillars could be fabricated.

 In July 1981 orders were placed to constructed the steel gates..

Also here they faced problems. The gates were very heavy and so a strong foundation was required.. To improve the resistance of the sand the sandy bottom was prepared for this resistance up to a depth of 15 meters. The special constructed vessel Mytilus was able to put long needles in the bottom. By vibration  the sand closed in and formed a prpoer foundation to withstand the weights of the steel barriers. The treatment of the sand lasted from the beginning of 1980 until the end of 1982.

After the sandy bottom was prepared it had to be reinforced and levelled. A specially for this purpose plant was constructed on the Neeltje Jans.  The plant produced artificial filled with a variety of shingles.

The mats were put in position by two specialized vessels the "Cardium" and the "Dos. 1". In addition the stone and the asphalt dump barge " Jan Heijmans" filled the gaps in between the mats with different type of stones. The mats are positioned  between November . '82 and June  '84.

When the total carpet of mats are ready the pillar can be positioned. For the construction of the pillars a total number of three large  15 meters deep construction docks are available.. In April 1979 they  started with the construction of the first pillars in the building dock. After having constructed all required pillars in 1983 the docks were flooded allowing the special constructed lift vessel "Ostrea" to start with the positioning of the pillars.

In Augustus 1983 the first of the 65 pillars are put into position. Finally a total of 16 in the North shutter hole, 17 in the middle shutter hole Schaar and 32 in the South Shutter hole Roompot. The 66th pillar was just a spare one and wasn't used..

By connection the pillars the final  weir was born.  The most important part are the steel movable gates which can be opened and closed. The gate exist of a huge tube construction and on Augustus  29 1984, the large sheerlegs "taklift 4" positioned the first gate and on  June  26 1986 the last gate was positioned In 1987  "European steelprice". was awarded for the inventive construction of the gates.

 

The Oosterschelde kering

Finally the day is there:  On October 4 1986 the Queen of the Netherlands Beatrix  the storm barrier was officially put in service. Together with the Minister of Transport and Public Works Miss  Nelie Kroes and the Director- General of Rijkswaterstaat Mr.  J. v. Dixhoorn  she speaks the historic words: "the storm barrier is closed . The delta works are ready. Zeeland is safe."

On 1 January 1987 the Delta Service hand over the storm barrier to Rijkswaterstaat of  Zeeland. The road on the weir was constructed later. On the fifth of November  1987 Princes Juliana opens the road passage by normal traffic. In July 1988 the last activities at the storm barrier are completed.  

Back to main menu of the delta works.