BRABANT FIGHTS AGAINST WATER Sorry, your browser doesn't support Java(tm).

 

 

                         The Grevelingen        

                                               

 

The activities as part of the delta plan are moving more inland after the success by Veerse gat. Namely the closing of the Grevelingen with a dam between Schouwen-Duiveland and Goeree-Overflakkee. The dam will have a length more then 6 kilometers.  

The operation starts in 1958. As usual they start to build a construction dock. The construction dock is situated close to the town of Bruinisse .

At this location also the construction starts of a excavation for the locks with dimensions  of 125 meters by 16 meter    

During the construction of the locks works continued to prepare the initial phase of the barrier. The barrier is constructed on the " Plaat van Oude Tonge [ sandbank]."  After this part of the dam is completed there are still 3 openings.  One has a length of 400 meters in way of the "Plaat van Oude Tonge and a double opening at the site of the Sint Jacob en Krammer.   

In 1961 the barrier at the Oude-Tonge is completed. In the southern part of the opening a threshold is created For this purpose the engineers uses old materials such as willow tree sinker but they also used new materials such as plastic asphalt and nylon.,

For Bruinisse community a lot changes

In May 1962  the gap between the sandbank  of Oude-tonge and the new locks are closed. The barrier however has not been completed yet because there are still two openings left on the  Goeree-Overflakkee site. A few ideas were promoted.. The initial idea was a bridge construction to allow trucks to dump shingles into the opening of the barrier.

A new idea developed namely a cable car.!!!!

The intention to use the cable car over the stretch of water and then the gondola (cars) to carry the stones and dump them at the appropriate position in the water.

The cable car was manufactured in France and cost 8,2 million Dutch guilders. The initial cost for the cable car was only budgeted on 5,8 million Dutch Guilder however as a 9 cm cable parted the operation faced considerable delays and the costs exaggerated enormously.

During the construction of the barrier a cable car was used.

During January the fate strikes. Because of a winter storm part of all the Construction got destroyed. Although the set back in the construction the operation recovered and part of the works was re-established. In total a quantity of 170.000 ton of material was dumped. After the dumping a layer of sand was put on top.       

So...the barriers finally completed in 1965.

 

Go back to the main menu of the delta works.