Spending

 

 

Spending for 2000

$188 million 15,000-seat indoor concert venue to exceed the entertainment centre: fourth biggest of the Olympics facilities.

Velodrome ($20 million): due for completion March 1999

Tennis Centre: Tenders yet to be called

Equestrian Centre: Horsley Park: Due for completion March 1998 $31 million

$463 million stadium tender to multiplex consortium

$ 69 million Olympic rail link tenders called

$134 million multi-use sports arena tenders to be called

$325 million showground sports hall due completion 1998

Athletics centre Opened 1994

Aquatics centre opened 1994

Media Village future still being determined

Regatta Centre Penrith $28.3 million stage 3 due finish 1996-1997

Shooting Centre Holsworthy due for completion March 1998

Hockey centre construction due to start late 1997

$1 billion worth of infrastructure (roads, burying powerlines, services. Tenders called progressively $8.5 million rail loop for completion early 1998)

*Clean up work at Homebush will cost $129 million, double bid estimate

*Relocating show to Homebush will cost $384 million $100 million more than it was originally estimated at

*Anticipated private sector funding for venues has decreased for the velodrome from $23.2 million to none (multi-use indoor arena ($85 million to $57 million) shooting sector ($8.1 million to none) and tennis centre $3.5 million to none)