The disaster of '53The DeltaworksThe plan for the DeltaworksFinancesDamsHollandse IJssel StormvloedkeringZandkreekdamVeersegatdamGrevelingendamBrouwersdamVolkerakdamHaringvlietdamOosterscheldedamSt. PhilipsdamOesterdamMaeslantkeringTimelineTotal summary of the damsWhat's changedGuided TourSearch over the siteHelpExtra stuffWho built this site, and how.

Zandkreekdam

GeneralThe planThe construction

The caissons were put on a foundation of stones and gravel to prevent them for sinking in the sandy bottom. The center part of the dam have to be higher than the rest because the water in the middle was deeper. This was done for the passing ships so this could be a shortcut to Vlissingen and Middelburg and they don’t have to sail by the North-Sea.

After placing 13 caissons and making a dike on top of the dam the Zandkreekdam was finished in 1960. The east side of the future Veerse Meer was closed.

 

Sizes of a caisson component:
11 meter long
7,5 meter wide
6 meter high

Cranes fill the caissons
Closing the east side of the Veerse Meer was easy. The current in this part was not high so they could work with blocks ( caissons) with uniform sizes. These blocks were hollow so they could float and positioned were they could sank in place. The caissons were produced on a special construction site near the village Kats on Noord-Beveland. They have tried to make these caissons in one piece but this was almost impossible for the walls of caissons must be as thin as possible so the concrete must be of an extreme high quality. They made the walls apart from the rest and in al later phase all these parts were assembled. To have caissons of different heights they made components of several sizes which could be stacked as Lego-blocks.

To prevent the caissons from disappearing in the sand they first have to make a threshold of big rocks and stones of different sizes. The small holes in between were filled with pebbles, gravel and sand to avoid leaking.