                        |
|

     
 |
Each column
weigh 18.000 tons. By using the right materials, a good plan, a perfect design and
intensive maintenance this flood barrier could survive at least 200 years. With this
barrier a serious flood was reduced to one time in 400 0 years. First the area where the barrier was planned the bottom was covered with
special designed an manufactured mats. For the first time in the world history a project
like this was done and special vessels for each activity had to be designed. |
The
threshold
The columns were not fixated on the threshold and the foot of each column was embedded by
stones. Also these stones were needed to close the gap between the slides and the
threshold. Several layers of stones were needed the lowest were the smallest. The top
layer was made of blocks each weighing between 6 and 10 tons. In two years more than 5
million tons of stones and rocks were dropped. The rocks were imported from Germany,
Finland an Belgium. The density of each stone lies between 2.8 and 3.0 kg/l.The columns
The hollow columns were prefabricated in a huge construction dock of 1km2. This dock was
surrounded by a dike and the bottom of the pit was 15.2 meters below sea level. |
 |
 |
Specifications:
weight: 8.000.000 kilograms
height: 30.25 meters to 38.75 meters
concrete: 7000 m3
time: 1.5 years per column The
construction dock was divided in several sections. When the columns in one section were
finished this section was flooded. A lifting vessel came in and transported the column to
its place on the threshold. Every two weeks they started to built another column.
A column was finished by placing
tops
horizontal top bars
horizontal bottom bars
the road pieces
|
 |
 |
This is a
hollow construction for the road on top and the equipment for moving the slides inside.
Each piece weigh 1.200.000 kilograms, is 45 meters long and 62 of these pieces were
needed. The top pieces
These are concrete constructions which are placed on top of each columns. The slides hang
on these pieces. For each column two top pieces are needed.
The horizontal bottom bar
This bar is 39 meters long and hollow and weigh 2.500.000 kilograms. It was placed on the
threshold between the columns. Just before placing small adaptations could be made on this
bar. After placing this bar was filled with sand. |
The
horizontal top bar
This bar is placed on top of the gate which is opened an closed by a slide. These hollow
concrete elements are 4 to 5 meters long and weigh 1.100.000 kilograms.The slides
The steel slides are placed between the columns. The have a length of 42 meters, the
height depends on its place in the barrier and is 5.9 to 11.9 meters. They weigh
between 300.000 and 500.000 kilograms.
To move the slides up and down a special hydraulic system had to be
designed. From one central point al the 124 hydraulic cylinders can be operated |
 |
|