                        |
|

      
 |
For
closing the south gully a cable-railway was needed which could do this in 9 or 10 weeks.
For building the south part of the dam 600.000 tons of stones and rocks were needed
Calculation showed that each hour 700 tons should be dropped. By building another dam they
have experienced that many things could go wrong so they decided they need a cable railway
with a capacity of 1200 tons per hour. |
| On the
mainland and on the Middenplaat a tower was built with rotating disks to lead the cable.
At each tower special loading docks for the cable-trolleys. In the middle of the
south gully two extra poles gave the cable extra strength. Cable railway plus loading
docks had a total length of 1759 meters. Each trolley had a capacity of 15 tons. Each
trolley must be able to transport 6 special made concrete blocks of 2.5 tons each. The
trolleys were provided with gas turbines instead of diesel engines. The trolleys had a
maximum speed of 7.5 meters per second. 240.000 concrete blocks were dropped in the
south gully and a permeable dam was created. Holes were filled and also the whole dam was
covered with sand. |
 |
|